How Long Does It Take to Build a Pool in South Shore FL? A Complete Timeline
Joey Sorrells
President, South Shore Pools & Luxury Outdoors · Licensed Pool Contractor CPC1460497

The Honest Answer
A custom inground pool in South Shore FL typically takes 3 to 6 months from contract signing to first swim, depending on project complexity, permit timelines, and weather. Here's how that breaks down phase by phase.
Phase 1: Design & Contract (2–4 Weeks)
Before anything touches the ground, we spend time understanding your vision. This phase includes a free in-home design consultation with Joey Sorrells, site evaluation, pool design development (layout, shape, features, finishes), 3D rendering (available upon request), and contract execution. Once signed, we move to permitting immediately.
Phase 2: Permitting (3–8 Weeks)
This is the most variable part of the timeline — largely outside our control. Hillsborough County and Manatee County require permits for all pool construction. Typical processing: 3–8 weeks. We submit complete, accurate permit packages to minimize back-and-forth. Some HOA approvals run concurrently.
Phase 3: Layout & Excavation (3–5 Days)
With permits in hand, we mobilize quickly. Our crew marks out the pool footprint, calls in underground utilities locates, and begins excavation. For a standard pool, excavation typically takes 1–2 days.
Phase 4: Steel Reinforcement & Plumbing Rough-In (3–5 Days)
Our crew installs the steel rebar framework and runs all plumbing lines — returns, suction, main drain, and feature plumbing — before inspection.
Phase 5: Gunite/Shotcrete Shell (1–2 Days + 10-Day Cure)
Pneumatically applied concrete forms the shell to your exact design. The shell cures for 7–10 days before the next phase. This is when the pool really starts to look real.
Phase 6: Tile, Coping & Decking (1–2 Weeks)
Our tile and coping crew sets the waterline tile, installs coping around the perimeter, and builds out the surrounding deck. This phase has a major impact on the overall aesthetic.
Phase 7: Equipment Installation (2–3 Days)
The pump, filter, heater, automation system, and water features are installed, plumbed, and connected to power by our licensed electricians.
Phase 8: Interior Finish (1–2 Days + Startup)
The PebbleTec or other interior finish is applied. The pool is then filled (24–48 hours) and the chemical startup process begins.
Phase 9: Final Inspection & Handover (1–2 Weeks)
County final inspection, then we train you on your pool's systems and hand over the keys. You swim. You enjoy. You never look back.
Tips for a Faster Build
- Start HOA approvals before signing with us
- Make design decisions promptly
- Be home for county inspections
- Trust the process — we keep you updated weekly
The sooner you start, the sooner you swim. Schedule your free design consultation today or call (813) 995-3750. We're currently booking across Apollo Beach, Ruskin, Sun City Center, Riverview, and Brandon.

About the Author
Joey Sorrells
President & Licensed Pool Contractor · CPC1460497 · South Shore Pools & Luxury Outdoors
Joey Sorrells founded South Shore Pools & Luxury Outdoors with one goal: to bring resort-quality outdoor living to South Shore Tampa Bay homeowners. With 15+ years of hands-on experience designing and building custom inground pools, spas, and outdoor kitchens across Apollo Beach, Ruskin, Sun City Center, and the greater Tampa Bay area, Joey leads every project with integrity, craftsmanship, and a genuine love for what he builds.
Explore More from South Shore Pools

Ready to Begin?
Stop Dreaming,
Start Building
Contact us today to schedule your complimentary on-site design consultation. Serving Apollo Beach, Ruskin, Sun City Center, and the entire South Shore Tampa Bay area.
Licensed Pool Contractor · CPC1460497 · 15+ Years · 5-Star Rated · Joey Sorrells, President