How Long Does It Take to Build a Pool?
Joey Sorrells
President, South Shore Pools & Luxury Outdoors · Licensed Pool Contractor CPC1460497

How Long Does It Take to Build a Pool?
It's one of the first questions every homeowner asks: How long does it take to build a pool? The honest answer is: it depends. But for most custom inground pools in the South Shore area — Apollo Beach, Ruskin, Sun City Center, and Riverview — you're looking at 4 to 6 months from the day you sign your contract to your first swim.
In this guide, we'll walk you through every phase of pool construction, what causes delays, and how to make sure your project stays on schedule.
The Short Answer: Pool Build Timeline Overview
| Phase | Typical Duration | Cumulative (Month) |
|---|---|---|
| Design & Proposal | 1–2 weeks | Month 1 |
| Permitting | 4–6 weeks | Month 1–2 |
| Excavation | 1–2 days | Month 2 |
| Steel & Plumbing | 1–2 weeks | Month 2–3 |
| Gunite / Shotcrete Shell | 1–3 days | Month 3 |
| Curing Period | 3–4 weeks | Month 3–4 |
| Tile, Coping & Decking | 3–5 weeks | Month 4–5 |
| Equipment Installation | 1–2 weeks | Month 5 |
| Interior Finish (Plaster) | 1–3 days | Month 5–6 |
| Fill & Startup | 1–2 weeks | Month 6 |
| Total | 4–6 Months |
Note: This timeline starts from contract signing. Permitting alone accounts for 4–6 weeks of that window — and it begins immediately after you sign.
Phase-by-Phase Breakdown
Phase 1: Design & Proposal — Month 1 (1–2 Weeks)
Before any dirt moves, you'll work with your pool builder to finalize the design. This includes:
- Site visit and property measurements
- Pool shape, size, and feature selection (spa, waterfalls, sun shelf, etc.)
- Material selections (tile, coping, plaster, decking)
- Equipment specifications (pump, filter, heater, automation)
- Final contract and pricing
At South Shore Pools, we use 3D design renderings so you can visualize your pool before we break ground. This phase typically takes 1–2 weeks depending on how many revisions you need.
Phase 2: Permitting — Month 1–2 (4–6 Weeks)
This is the phase most homeowners don't anticipate. In Hillsborough County — which covers Apollo Beach, Ruskin, Sun City Center, and Riverview — the permit review process takes 4 to 6 weeks on average in 2026.
What happens during permitting:
- Contractor submits engineered pool plans to the county
- County reviews structural, electrical, and plumbing specifications
- Plans may require revisions (adds 1–2 weeks)
- Permit is issued and posted at the job site
Pro Tip: A reputable builder submits permit applications immediately after contract signing. At South Shore Pools, we file within 48 hours so we minimize wait time.
Phase 3: Excavation — Month 2 (1–2 Days)
Once the permit is in hand, the dig begins. Excavation is one of the fastest phases — most residential pools are fully excavated in a single day. The crew uses a backhoe to dig the pool shell to the engineered depth and shape.
What can slow excavation:
- Underground utilities requiring hand digging
- Unexpected rock formations (rare in South Shore, but possible)
- Limited access to backyard (narrow gates require smaller equipment)
Phase 4: Steel & Plumbing — Month 2–3 (1–2 Weeks)
After excavation, the steel rebar framework is installed to reinforce the pool shell. This is followed by rough plumbing — the pipes that carry water to and from your pump, filter, and features.
During this phase, the county inspector visits to approve the rebar and plumbing before the shell is sprayed. Scheduling the inspection adds a few days.
Phase 5: Gunite / Shotcrete Shell — Month 3 (1–3 Days)
This is the dramatic moment — the pool shell takes shape. A gunite crew sprays a mixture of concrete and sand at high pressure over the rebar framework, forming the structural shell of your pool.
The shell must then cure (harden) before it's ready for finishing. During the cure, your crew will wet the shell daily to prevent cracking.
Phase 6: Curing Period — Month 3–4 (3–4 Weeks)
Patience is required here. The gunite shell needs time to cure and achieve its full structural strength. During this period:
- The shell is kept wet to prevent cracking
- Decking sub-base may be prepared
- Equipment pad is poured
- Electrical rough-in may begin
Phase 7: Tile, Coping & Decking — Month 4–5 (3–5 Weeks)
This phase dramatically transforms how your pool looks. The waterline tile is set, the coping (edge material around the pool) is installed, and the deck surface (travertine, pavers, concrete) is laid.
This is typically the most time-consuming phase, especially if you've chosen:
- Custom mosaic tile designs
- Natural stone coping
- Large paver decks or outdoor living areas
- Attached spa or raised features
Phase 8: Equipment Installation — Month 5 (1–2 Weeks)
Your pump, filter, heater, salt system, automation controller, and lighting are installed on the equipment pad. Electrical connections are made and inspected by the county.
At South Shore Pools, we use premium equipment from Pentair and Hayward — properly sized for your pool's volume and feature set so it runs efficiently for years.
Phase 9: Interior Finish — Plaster or Pebble — Month 5–6 (1–3 Days)
The final interior surface is applied — whether standard plaster, quartz, or a premium pebble finish like PebbleTec or PebbleSheen. This is applied quickly (1–3 days) but requires an immediate startup process.
Phase 10: Fill, Startup & Chemistry Balancing — Month 6 (1–2 Weeks)
The pool is filled with water — for an average 15,000-gallon pool, this takes 24–48 hours. Once filled, your pool technician begins the startup chemical process, which takes 7–14 days of daily brushing and chemistry adjustments.
After startup is complete, your pool is ready to swim.
What Causes Pool Construction Delays?
Even with the best contractor, delays happen. Here are the most common causes:
1. Permit Delays (Most Common)
County permit backlogs can push timelines by weeks. There's not much a contractor can do except submit quickly and follow up regularly. We do both.
2. Rain and Weather
Florida's rainy season (June–September) can pause excavation, gunite, decking, and plastering. Certain phases simply cannot proceed in wet conditions.
3. Material Delays
Tile, coping, and specialty materials sometimes have lead times of 2–6 weeks. Choosing in-stock materials speeds things up significantly.
4. Change Orders Mid-Build
If you decide to add features (spa, fire pit, outdoor kitchen) after construction begins, it adds time and cost. Lock in your final design before the permit is submitted.
5. Inspector Scheduling
Multiple county inspections are required during construction. Scheduling delays at each inspection point can add days to the project.
6. Subcontractor Availability
Busy construction seasons (spring and early summer) can push out subcontractor schedules. Starting your project in fall or winter often results in faster completion.
How to Speed Up Your Pool Build
- Sign your contract and finalize your design early. The sooner you sign, the sooner we can pull the permit.
- Choose in-stock materials. Custom or imported tile and stone can add 2–6 weeks of wait time.
- Avoid mid-build change orders. Finalize your features before construction begins.
- Work with an established builder. Experienced contractors have preferred status with subcontractors and inspectors, which moves projects faster.
- Start in fall or winter. Less rain, less contractor demand, and faster inspections.
Pool Build Timeline: Frequently Asked Questions
How long does it take to build a pool in Florida?
In Hillsborough County (Apollo Beach, Ruskin, Sun City Center, Riverview), expect 4 to 6 months total from the day you sign your contract to your first swim.
How long does permitting take for a pool in Hillsborough County?
Currently 4–6 weeks for residential pool permits in 2026. This is the most variable phase of the timeline.
Can a pool be built faster than 4 months?
Rarely. Permitting alone takes 4–6 weeks, and the gunite curing period adds another 3–4 weeks. Even the fastest builds require at least 3.5–4 months from contract to completion.
What time of year is best to build a pool in Florida?
Fall (October–December) is ideal. Fewer rain delays, shorter inspector wait times, and you'll be ready to swim when summer arrives.
Do I need to be home during pool construction?
Not every day. Your contractor will update you at each milestone. Most homeowners are not home during the day, and that's perfectly fine. We provide regular photo updates and progress reports.
What's the most common delay in pool construction?
Permits, by far. The county review process is the least controllable variable in any pool build. A good builder submits quickly and follows up proactively.
Ready to Start Your Pool?
At South Shore Pools and Luxury Outdoors, we've built hundreds of custom pools across Apollo Beach, Ruskin, Sun City Center, and Riverview. We're known for transparent timelines, clear communication, and delivering projects on schedule.
When you work with us, you'll receive:
- A detailed project timeline before we break ground
- Regular construction updates with photos
- A dedicated project manager as your point of contact
- Honest answers when delays occur (and a plan to recover)
Schedule your free consultation today and let's talk about bringing your dream pool to life.

About the Author
Joey Sorrells
President & Licensed Pool Contractor · CPC1460497 · South Shore Pools & Luxury Outdoors
Joey Sorrells founded South Shore Pools & Luxury Outdoors with one goal: to bring resort-quality outdoor living to South Shore Tampa Bay homeowners. With 15+ years of hands-on experience designing and building custom inground pools, spas, and outdoor kitchens across Apollo Beach, Ruskin, Sun City Center, and the greater Tampa Bay area, Joey leads every project with integrity, craftsmanship, and a genuine love for what he builds.
Explore More from South Shore Pools

Ready to Begin?
Stop Dreaming,
Start Building
Contact us today to schedule your complimentary on-site design consultation. Serving Apollo Beach, Ruskin, Sun City Center, and the entire South Shore Tampa Bay area.
Licensed Pool Contractor · CPC1460497 · 15+ Years · 5-Star Rated · Joey Sorrells, President